Construction Project Update: June 30, 2026
Stay up to date with current construction projects and the latest progress across the community. Updates will be provided on a bi-weekly basis.
- Mount Brydges Wastewater Treatment Facility Upgrades
- Shop drawings/project documentation submissions ongoing
- Contractor mobilization June 17th, 2026
- Erosion/sediment controls, and dewatering operations installed
- Initial site preparation for equipment/material laydown areas, office trailers, washroom facilities, etc.
- Beech Street Reconstruction
- Storm sewer, including storm PDC (private drain connections) installations completed
- Sanitary sewer, including sanitary PDC (private drain connections) installations completed
- Watermain installation and tie-in connections completed
- Water services converted from temporary watermain to new watermain – installations in progress
- Parkhouse Drive Reconstruction
- Contractor mobilization June 15th, 2026
- Tree removals/pruning and tree protection fencing installed
- Temporary watermain installation in progress
- Erosion/sediment controls, and dewatering operations in progress
If you have any questions about this application please contact Andrew Haagsma at ahaagsma@strathroy-caradoc.ca.