Construction Project Update: June 30, 2026

Stay up to date with current construction projects and the latest progress across the community. Updates will be provided on a bi-weekly basis. 

  1. Mount Brydges Wastewater Treatment Facility Upgrades
    • Shop drawings/project documentation submissions ongoing
    • Contractor mobilization June 17th, 2026
    • Erosion/sediment controls, and dewatering operations installed
    • Initial site preparation for equipment/material laydown areas, office trailers, washroom facilities, etc.
  1. Beech Street Reconstruction
    • Storm sewer, including storm PDC (private drain connections) installations completed
    • Sanitary sewer, including sanitary PDC (private drain connections) installations completed
    • Watermain installation and tie-in connections completed
    • Water services converted from temporary watermain to new watermain – installations in progress
  1. Parkhouse Drive Reconstruction 
    • Contractor mobilization June 15th, 2026
    • Tree removals/pruning and tree protection fencing installed
    • Temporary watermain installation in progress
    • Erosion/sediment controls, and dewatering operations in progress

If you have any questions about this application please contact Andrew Haagsma at ahaagsma@strathroy-caradoc.ca.